The German shipyard FSG Shipyard delivered the RoRo ferry SEAROAD I to Australian operator SeaRoad on 23 November, approximately three years behind schedule. SEAROAD I will be deployed on the Melbourne–Devonport route.
SEAROAD I was ordered in September 2021, with delivery scheduled for the fourth quarter of 2023. The first steel was cut on 20 May 2022 at Flensburger Schiffbau-Gesellschaft, followed by the keel-laying ceremony on 27 February 2023. After that, progress on the construction fell silent as Flensburger Schiffbau-Gesellschaft once again ran into financial difficulties.
Following yet another insolvency, the new FSG Shipyard was able to hold a restart ceremony in April 2025. On 7 November 2025, SEAROAD I was finally launched. The new delivery date was set for July 2026, but this deadline was also not quite met.
Source: SeaRoad