SEAROAD I delivered to SeaRoad

SEAROAD I in Flensburg on 29/3-2026. Photo: Michael Koefoed-Hansen

The German shipyard FSG Shipyard delivered the RoRo ferry SEAROAD I to Australian operator SeaRoad on 23 November, approximately three years behind schedule. SEAROAD I will be deployed on the Melbourne–Devonport route.

SEAROAD I was ordered in September 2021, with delivery scheduled for the fourth quarter of 2023. The first steel was cut on 20 May 2022 at Flensburger Schiffbau-Gesellschaft, followed by the keel-laying ceremony on 27 February 2023. After that, progress on the construction fell silent as Flensburger Schiffbau-Gesellschaft once again ran into financial difficulties.

Following yet another insolvency, the new FSG Shipyard was able to hold a restart ceremony in April 2025. On 7 November 2025, SEAROAD I was finally launched. The new delivery date was set for July 2026, but this deadline was also not quite met.

Source: SeaRoad

About Michael Koefoed-Hansen

Editor and owner of FerryWire. Has published 3 books about Danish ferry traffic at the Starnia publishing house, and has run the website “The ferry site” since 1998. “The ferry site” is today one of the largest private websites with information about ferries.

View all posts by Michael Koefoed-Hansen →